Modelo de Alocação de Atividades de Testes: Uma abordagem Heurística com Teoria das Filas em Cenário Real de Desenvolvimento

Nívea Pereira Freitas, Raquel Da Mota Batista, Leonardo Tetsuya Shintaku, Dayane Cristine Leite Behm, Alipio Sales Carvalho, Isabel Carril Gama
SchedulingParallel machinesQueueing theoryGreedy heuristic

Resumo

Manual test-activity allocation on agile teams has poor scalablity, traceability and load balance. We formalize the problem as a multi-objective unrelated-parallel-machine scheduling problem with eligibility, deadline and workload constrains, and propose a three-phase heuristic: (i) M/M/c queueing-theory sizing, (ii) greedy construction driven by a priority score, and (iii) 2-opt local search refinement. On real data (26 testers, 852h of demand), the approach cuts workload standart deviation by 22,5%, overload by 36,5% and allocation time from 2h to 30 s.